In April 2009 Mather and Stuart undertook the provision of temporary power supplies for a 12 hour period, to facilitate the replacement of the high voltage transformer equipment feeding North Manchester General hospital.
The work involved the provision, electrical connection and operation of three 1000Kva trailer mounted generators. Two machines operating in parallel were used to supply the primary load and an additional machine provided back-up to the site emergency generator.
The work was completed in a very professional manner, to a rigid time table without any problems.
The quality of the equipment and service provided by Mather and Stuart was excellent and I would not hesitate to recommend them for any similar temporary power supply projects.
"